Free renewal for one year
When it comes to the strong points of our Construction-Manager training materials, free renewal must be taken into account. Free renewal refers to that our Construction-Manager exam dumps provides customers who have made a purchase for our Construction-Manager study guide renewal in one year for free. I have to say that no other exam learning material files can be so generous as to offer you free renewal for the whole year. However, our CMAA Construction-Manager training materials do achieve it because they regard the interests of the general public as the paramount mission. Therefore, they just do their best to serve you wholeheartedly. That is why they would like to grant the privilege of free renewal for one year to the general customers. In addition, our Construction-Manager exam dumps specially offer customers some discounts in reward of the support from customers.
Fast delivery
Unlike other kinds of exam files which take several days to wait for delivery from the date of making a purchase, our Construction-Manager study guide can offer you immediate delivery after you have paid for them. The moment you money has been transferred into our account, and our system will send our CMAA Construction-Manager training materials to your mail boxes so that you can download them directly. With so many experiences of tests, you must be aware of the significance of time related to tests. (Construction-Manager exam dumps) Time is actually an essential part if you want to pass the exam successfully as both the preparation of Construction-Manager study guide and taking parting part in the exam need enough time so that you accomplish the course perfectly well.
After purchase, Instant Download Construction-Manager Dumps: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Do you still remember your dream? Do you still remember that once upon a time you even had the ambition to conquer the universe? (Construction-Manager training materials) But now, you are so upset that you even forget who you are and where you come from. Come on, baby! Don't lose heart as everything has not been settled down and you still have time to prepare for the Construction-Manager actual test. You still have the choice, and that is our CMAA Construction-Manager exam dumps. With our Construction-Manager study guide, you can be the one who laughs at last. The reasons are follows.
High hit ratio
Our Construction-Manager training materials, after so many years of experience concerning the question making, have developed a well-organized way to compile the frequently tested points and the latest heated issues all into our Construction-Manager exam dumps files. As a result, the majority of our questions are quite similar to what will be tested in the real exam. Customers who have used our Construction-Manager study guide materials to study hard for the coming exam will be quite familiar to those tested points since they have received a lot of training of the same kind from our Construction-Manager latest dumps. What's more, as our exam experts of Construction-Manager study materials all are bestowed with great observation and profound knowledge, they can predict accurately what the main trend of the exam questions is, which to a considerable extent helps to achieve the high hit ratio of our Construction-Manager training online.
CMAA Construction-Manager Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Professional Practice | 10% | - Ethics and Professional Conduct
|
| Topic 2: Program & Project Management | 20% | - Project Planning and Coordination
|
| Topic 3: Time Management | 10% | - Delay Analysis
|
| Topic 4: Cost Management | 10% | - Value Engineering
|
| Topic 5: Safety Management | 10% | - Safety Programs and Policies
|
| Topic 6: Risk Management | 10% | - Risk Identification and Assessment
|
| Topic 7: Quality Management | 10% | - Standards Compliance
|
| Topic 8: Technology | 5% | - Construction Technology
|
| Topic 9: Sustainability | 5% | - Energy Efficiency
|
| Topic 10: Contract Administration | 10% | - Contract Types and Structures
|
CMAA Certified Construction Manager (CCM) Sample Questions:
1. Which of the following provides details about the front-end activities of the project during the pre-design and design phases, and highlights major project milestones such as substantial and final completion?
A) Master Schedule
B) Milestone Schedule
C) Baseline Schedule
D) As-Built Schedule
2. Contract administration includes, but is not limited to, planning for implementation of drawings, specifications, and
A) permits.
B) owner's scope of work.
C) licenses.
D) standards.
3. Who owns the float in a typical project critical path schedule?
A) Contractor
B) Project
C) Construction manager
D) Owner
4. The current construction market is extremely busy, and the trade/sub-contractors are being very selective in the projects they bid on. What options do owners have when the marketplace is vastly different from when their project was a concept to when its ready to be advertised?
A) Market conditions should not be a factor in when a project is advertised.
B) Consider the impacts of current market conditions and revise project strategy.
C) Postpone advertising for one year.
D) Advertise the project and award to lowest bidder.
5. At what stage of the design phase shall the CM conduct a constructability review?
A) 30% design stage
B) Throughout the design process including 100% design documents
C) 60% design stage
D) 90% design stage
Solutions:
| Question # 1 Answer: B | Question # 2 Answer: D | Question # 3 Answer: B | Question # 4 Answer: B | Question # 5 Answer: B |