NEW QUESTION 14
What information does the SAP Fiori apps reference library provide? Note: There are 2 correct Answers to this question.
- A. Transaction codes that are no longer used
- B. Key installation and configuration information for each app
- C. Information about previous versions of an app
- D. Accelerators with configuration building blocks
Answer: B,C
NEW QUESTION 15
Which of the following elements are used during forward scheduling in material requirements planning? Note:
There are 2 correct Answers to this question.
- A. Goods receipt processing time
- B. Total replenishment lead time
- C. Shipping processing time
- D. Purchasing processing time
Answer: A,D
NEW QUESTION 16
Which of the following business functions are supported by SAP S/4HANA Settlement Management? Note:
There are 3 correct Answers to this question
- A. Business-volume-related rebates
- B. Advance payments
- C. Calendar-based settlement
- D. Evaluated receipt settlement
- E. Accrual conditions
Answer: B,C,D
NEW QUESTION 17
What can cause an open item on the goods receipt/invoice receipt (GR/IR) account?
- A. Difference between quantity delivered and quantity invoiced for a purchase order item
- B. Difference between material valuation price and invoice price for a purchase order item
- C. Difference between purchase order price and invoice price for a purchase order item
- D. Difference between quantity ordered and quantity invoiced for a purchase order item.
Answer: A
NEW QUESTION 18
How does inventory management differ in SAP S/4HANA compared to SAP ERP? Note: There are 2 correct Answers to this question.
- A. MKPF and MSEG document tables are no longer displayed.
- B. Material ledger is obligatory for material valuation.
- C. MARC and MARD tables no longer contain stock aggregates.
- D. Material ledger is recommended for material valuation.
Answer: B,C
NEW QUESTION 19
Which of the following features are new in SAP S/4HANA Sourcing and Procurement compared to SAP ERP? Note: There are 2 correct Answers to this question.
- A. You can send a request for quotation to external sourcing platforms such as SAP Ariba Sourcing.
- B. You must enter a supplier number in a request for quotation.
- C. You can maintain several offers from different suppliers for one request for quotation.
- D. You can link several requests for quotation (RFQ) using a collective number in the RFQ header.
Answer: A,C
NEW QUESTION 20
In which processes can a bill of material (BOM) be used to determine the components of a finished product?
Note: There are 3 correct answer
- A. Product costing
- B. Material requirements planning
- C. Third-party order processing
- D. Supplier consignment
- E. Subcontracting
Answer: A,B,E
NEW QUESTION 21
To which of the following objects can you assign a field reference to control field selection for material master records? Note: There are 2 correct Answers to this question.
- A. Industry sector
- B. MRP area
- C. Plant
- D. Company code
Answer: A,C
NEW QUESTION 22
In what ways can you personalize the Procurement Overview Page SAP Fiori app in SAP S/4HANA? Note:
There are 3 correct Answers to this question.
- A. Change the position of cards.
- B. Filter information on a card.
- C. Change the set of cards.
- D. Hide an existing card.
- E. Extend the set with a new card.
Answer: A,B,D
NEW QUESTION 23
Which of the following must you do before the system can check the minimum remaining shelf life during the goods receipt for a purchase order (PO)?
Note: There are 2 correct Answers to this question.
- A. Activate batch management for the material.
- B. Enter the earliest acceptable expiration date in the PO item.
- C. Activate the shelf life expiration date (SLED) check in customizing.
- D. Enter the remaining shelf life in the material master record
Answer: C,D
NEW QUESTION 24
What must you consider when you define a storage location? Note: There are 2 correct Answers to this question.
- A. A storage location must be assigned to a warehouse number.
- B. A storage location always has the same address as the plant.
- C. A storage location always belongs to a plant.
- D. The storage location key must be unique within a plant.
Answer: C,D
NEW QUESTION 25
Which of the following are restrictions of material-to-material postings? Note: There are 3 correct Answers to this question.
- A. The postings can be made only from unrestricted-use stock of the issuing material to unrestricted-use stock of the receiving material.
- B. The postings can be made only if the stock of the issuing material is in the same storage location as the stock of the receiving material.
E, The postings cannot be pre-planned with a reservation. - C. The postings can be made only between materials with the same material type.
- D. The postings can be made only in a single step.
Answer: A,D
NEW QUESTION 26
Which field in the material master record controls whether external requirements should be included in the net requirements calculation during reorder point planning?
- A. MRP group
- B. MRP profile
- C. MRP controller
- D. MRP type
Answer: A
NEW QUESTION 27
Which of the following statements describe the provisioning of components to a subcontractor? Note: There are 3 correct Answers to this question.
- A. The provisioning of components can be supported by a one-step procedure or a two-step procedure.
- B. The provisioning of components corresponds to a transfer posting from unrestricted-use stock to subcontracting stock.
- C. The inventory of components provided to the subcontractor is managed as consignment stock.
- D. The inventory of components provided to the subcontractor is non-valuated.
- E. The inventory of components provided to the subcontractor is managed at plant level.
Answer: B,C,D
NEW QUESTION 28
What must you do to enable the creation of Just-in-Time (JIT) delivery schedule lines for a scheduling agreement? Note: There are 2 correct Answers to this question.
- A. Use a document type for the scheduling agreement for which release documentation has been activated.
- B. Maintain the MRP views in the master record of the material used in the scheduling agreement item.
- C. Set the JIT Indicator field in the purchasing info record of the material and supplier used in the scheduling agreement
- D. Set the JIT indicator in the master record of the material used in the scheduling agreement item.
Answer: C,D
NEW QUESTION 29
Which of the following functions does the scheduling agreement with release documentation enable? Note:
There are 2 correct Answers to this question.
- A. Generate Just-in-Time delivery schedules automatically using MRP
- B. Generate delivery schedules using a release creation profile.
- C. Generate delivery schedules using a background job.
- D. Generate forecast delivery schedules automatically using MRP.
Answer: B,D
NEW QUESTION 30
Which of the following are required to enable account changes when posting an invoice with reference to a purchase order item with account assignment?
Note: There are 2 correct Answers to this question.
- A. Choose a valuated goods receipt in the purchase order item and post the invoice before the goods receipt.
- B. Allow account assignment changes during invoice receipt in customizing for the account assignment category.
- C. Choose multiple account assignment combined with a partial invoice indicator in the purchase order item.
- D. Choose either a non-valuated goods receipt or no goods receipt posting in the purchase order item.
Answer: B,D
NEW QUESTION 31
Which of the following SAP Fiori apps are available for an employee to carry out the self-service requisitioning process in SAP S/4HANA? Note: There are 3 correct Answers
- A. Confirm Receipt of Goods
- B. Post Goods Receipt for Purchase Order
- C. Upload Supplier Invoice
- D. Create Purchase Requisition
- E. Manage Supplier Invoices
Answer: A,B,D
NEW QUESTION 32
Your purchasing organization intends to procure a finished product from a supplier. The supplier will manufacture the product using components provided by your company. Which process do you use for this scenario?
- A. Third-party
- B. External processing
- C. Consignment
- D. Subcontracting
Answer: D
NEW QUESTION 33
To what object can you assign a purchasing group? a. b. c. d.
- A. Plant
- B. Purchasing organization
- C. Material
- D. Supplier
Answer: C
NEW QUESTION 34
Which of the following actions can you perform with transaction MIGO? Note: There are 3 correct Answers to this question.
- A. Create a stock transport order.
- B. Cancel a material document.
- C. Enter physical inventory count.
- D. Release GR blocked stock.
- E. Create a return delivery.
Answer: B,D,E
NEW QUESTION 35
Where can you specify whether consumption-based planning or requirements-based planning will be performed? Note: There are 2 correct Answers to this question.
- A. In the customizing of the plant parameters
- B. In the MRP area data of a material
- C. In the plant data of a material
- D. On the initial screen of the planning run
Answer: A,B
NEW QUESTION 36
Which of the following capabilities does Ariba Network offer for invoicing in SAP S/4HANA? Note: There are 2 correct Answers to this question.
- A. Supplier invoices uploaded to Ariba Network appear directly in SAP S/4HANA as drafts.
- B. Supplier invoices sent using Ariba Network are posted directly in SAP S/4HANA.
- C. Suppliers can monitor their invoices and payment status in Ariba Network.
- D. Using Ariba Network speeds up invoicing, but still requires additional paper invoices to be sent.
Answer: B,C
NEW QUESTION 37
Which of the following does the material type control? Note: There are 2 correct Answers to this question.
- A. Whether split valuation is allowed for the material
- B. Which procurement type(s) the material can have
- C. Whether batch management is active for the material
- D. Whether the material number assignment is internal or external
Answer: B,D
NEW QUESTION 38
......