NEW QUESTION 28
Your quality department detect a deviation in a raw material batch. Unfortunately, this batch has already been used in producion. How can you indentify all affected finish goods stocks?

  • A. Use batch determination.
  • B. Use the batch information cockpit.
  • C. Use the material where-used report.
  • D. Use the material staging report.

Answer: B

 

NEW QUESTION 29
Which business processes are affected by setting in the order type-dependent parameters?

  • A. Select master data.
  • B. Implement engineering changes.
  • C. Define integration to cost accounting.
  • D. Intiate quality inspections.

Answer: A,C

 

NEW QUESTION 30
Which times elements does MRP consider in backward scheduling to determine he order dates for components from dependent requirements?

  • A. Operation duration
  • B. Planed delivery time
  • C. In-house production time
  • D. Total replenishment lead time

Answer: B,C

 

NEW QUESTION 31
Your proyect team decides to use a make-to-order planning strategy for strategic in discrete manufacturing.
What is the impact of this decision?

  • A. A sales-order-specific planning run is required.
  • B. Net requirement calcualtion is sales-order specific.
  • C. Storage location MRP areas are required.
  • D. Production orders specific stock is created

Answer: A,B,D

 

NEW QUESTION 32
Which master data object governs the relationship between supply source and demand source in the Kanban process?

  • A. Production supply area
  • B. Replenishment strategy
  • C. Rate routing
  • D. Control cycle

Answer: D

 

NEW QUESTION 33
When can the automatic material availability check occur in a production order?

  • A. At order release
  • B. At order settlement
  • C. At order creation
  • D. At order confirmation

Answer: A,C

 

NEW QUESTION 34
Which of the following processes lead to an entry in the MRP planing file?

  • A. Creation of sales order
  • B. Change of the material's procurement type
  • C. Change of the storage bin
  • D. Creation of purchasing contract
  • E. Creation of dependent requirements

Answer: A,B,E

 

NEW QUESTION 35
What is a work center hierarchy in planning in SAP S/4HANA?

  • A. A group of work centers in a parallel sequence that is used to split production quantities and work on them in parallel
  • B. A group of work centers in a production line being used in sequence for production
  • C. A group of alternative work centers providing a cumulative available capacity for production.
  • D. A group of alternative work centers for production, structured in hierarchy levels by priorities

Answer: C

 

NEW QUESTION 36
Which of the following elements does MRP take into account during net requirement calculation?

  • A. Safety stock
  • B. Maximum stock level
  • C. Purchase orders
  • D. Lot size

Answer: A,D

 

NEW QUESTION 37
You want to use capacity availability checks for production orders. Which settings have to be made for this?

  • A. An overall profile must be assigned in the checking control.
  • B. The PRT Availability Check must be set in the checking control.
  • C. The Relevant for Finite Scheduling indicator must be set
  • D. A checking rule must be assigned in the checking control

Answer: A,C

 

NEW QUESTION 38
For which categories can you define BOMs in SAP S/4HANA?

  • A. Document Structure
  • B. Sales order
  • C. Work Center
  • D. Class

Answer: A,B

 

NEW QUESTION 39
What does the material type influence?

  • A. Whether the material is produced in-house, procured externally or bouth
  • B. Which material master views can be maintained
  • C. Which plant specific status is allowed
  • D. Which document types are allowed

Answer: A,B

 

NEW QUESTION 40
Why would you use phantom assemblies?

  • A. To make the assignment of components easier
  • B. To reduce the number of material masters
  • C. To reduce the number of changes required in bills of materials
  • D. To simplify the structure of bills of materials
  • E. To increase the number of planning levels

Answer: A,C,D

 

NEW QUESTION 41
You have a schedule agreement whit a vendor. You want classic MRP to automatically create schedule lines in case of material shortage.
What must you do?

  • A. Add the agreement to the quota arrangement and mark it for MRP revalance.
  • B. Add the agreement to the source list and mark it for MRP revalance.
  • C. Set the creation indicator for purchase requisitions on initial screen of MRP run
  • D. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.

Answer: B,D

 

NEW QUESTION 42
What does forecasting in demand planning cycle include?

  • A. One-off events
  • B. Past sales order quantites
  • C. Past procurment quantities
  • D. Past quotation quantities
  • E. Market intelligence

Answer: A,B,E

 

NEW QUESTION 43
Your project used process orders for the production of liquid chemicals.
What can you define to ensure that the production flow happens only in physically connected tanks?

  • A. Work center hierarchy
  • B. Operation network
  • C. Setup matrix
  • D. Resource network

Answer: A

 

NEW QUESTION 44
Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing?

  • A. Run MRP with automatic selection of production version.
  • B. Run PP/DS heuristics for repetitive manufacturing.
  • C. Assign planned orders manual lying the planning table.
  • D. Run MRP with quota arrangement.

Answer: B,D

 

NEW QUESTION 45
You set up a material as a phantom assembly by entering the special procurement key in the material master.
How can you switch off the phantom assembly in a specific bill of material (BOM)?

  • A. Change the special procurement key of the phantom assembly in the BOM.
  • B. Change the item category of the phantom assembly in the BOM.
  • C. Change the explosion type of the phantom assembly in the BOM.
  • D. Change the phantom item indicator for the phantom assembly in the BOM.

Answer: C

 

NEW QUESTION 46
......