
Share Latest Feb-2023 C_TS422_2021 DUMP with 82 Questions and Answers
PDF Dumps 2023 Exam Questions with Practice Test
NEW QUESTION 28
Your quality department detect a deviation in a raw material batch. Unfortunately, this batch has already been used in producion. How can you indentify all affected finish goods stocks?
- A. Use batch determination.
- B. Use the batch information cockpit.
- C. Use the material where-used report.
- D. Use the material staging report.
Answer: B
NEW QUESTION 29
Which business processes are affected by setting in the order type-dependent parameters?
- A. Select master data.
- B. Implement engineering changes.
- C. Define integration to cost accounting.
- D. Intiate quality inspections.
Answer: A,C
NEW QUESTION 30
Which times elements does MRP consider in backward scheduling to determine he order dates for components from dependent requirements?
- A. Operation duration
- B. Planed delivery time
- C. In-house production time
- D. Total replenishment lead time
Answer: B,C
NEW QUESTION 31
Your proyect team decides to use a make-to-order planning strategy for strategic in discrete manufacturing.
What is the impact of this decision?
- A. A sales-order-specific planning run is required.
- B. Net requirement calcualtion is sales-order specific.
- C. Storage location MRP areas are required.
- D. Production orders specific stock is created
Answer: A,B,D
NEW QUESTION 32
Which master data object governs the relationship between supply source and demand source in the Kanban process?
- A. Production supply area
- B. Replenishment strategy
- C. Rate routing
- D. Control cycle
Answer: D
NEW QUESTION 33
When can the automatic material availability check occur in a production order?
- A. At order release
- B. At order settlement
- C. At order creation
- D. At order confirmation
Answer: A,C
NEW QUESTION 34
Which of the following processes lead to an entry in the MRP planing file?
- A. Creation of sales order
- B. Change of the material's procurement type
- C. Change of the storage bin
- D. Creation of purchasing contract
- E. Creation of dependent requirements
Answer: A,B,E
NEW QUESTION 35
What is a work center hierarchy in planning in SAP S/4HANA?
- A. A group of work centers in a parallel sequence that is used to split production quantities and work on them in parallel
- B. A group of work centers in a production line being used in sequence for production
- C. A group of alternative work centers providing a cumulative available capacity for production.
- D. A group of alternative work centers for production, structured in hierarchy levels by priorities
Answer: C
NEW QUESTION 36
Which of the following elements does MRP take into account during net requirement calculation?
- A. Safety stock
- B. Maximum stock level
- C. Purchase orders
- D. Lot size
Answer: A,D
NEW QUESTION 37
You want to use capacity availability checks for production orders. Which settings have to be made for this?
- A. An overall profile must be assigned in the checking control.
- B. The PRT Availability Check must be set in the checking control.
- C. The Relevant for Finite Scheduling indicator must be set
- D. A checking rule must be assigned in the checking control
Answer: A,C
NEW QUESTION 38
For which categories can you define BOMs in SAP S/4HANA?
- A. Document Structure
- B. Sales order
- C. Work Center
- D. Class
Answer: A,B
NEW QUESTION 39
What does the material type influence?
- A. Whether the material is produced in-house, procured externally or bouth
- B. Which material master views can be maintained
- C. Which plant specific status is allowed
- D. Which document types are allowed
Answer: A,B
NEW QUESTION 40
Why would you use phantom assemblies?
- A. To make the assignment of components easier
- B. To reduce the number of material masters
- C. To reduce the number of changes required in bills of materials
- D. To simplify the structure of bills of materials
- E. To increase the number of planning levels
Answer: A,C,D
NEW QUESTION 41
You have a schedule agreement whit a vendor. You want classic MRP to automatically create schedule lines in case of material shortage.
What must you do?
- A. Add the agreement to the quota arrangement and mark it for MRP revalance.
- B. Add the agreement to the source list and mark it for MRP revalance.
- C. Set the creation indicator for purchase requisitions on initial screen of MRP run
- D. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
Answer: B,D
NEW QUESTION 42
What does forecasting in demand planning cycle include?
- A. One-off events
- B. Past sales order quantites
- C. Past procurment quantities
- D. Past quotation quantities
- E. Market intelligence
Answer: A,B,E
NEW QUESTION 43
Your project used process orders for the production of liquid chemicals.
What can you define to ensure that the production flow happens only in physically connected tanks?
- A. Work center hierarchy
- B. Operation network
- C. Setup matrix
- D. Resource network
Answer: A
NEW QUESTION 44
Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing?
- A. Run MRP with automatic selection of production version.
- B. Run PP/DS heuristics for repetitive manufacturing.
- C. Assign planned orders manual lying the planning table.
- D. Run MRP with quota arrangement.
Answer: B,D
NEW QUESTION 45
You set up a material as a phantom assembly by entering the special procurement key in the material master.
How can you switch off the phantom assembly in a specific bill of material (BOM)?
- A. Change the special procurement key of the phantom assembly in the BOM.
- B. Change the item category of the phantom assembly in the BOM.
- C. Change the explosion type of the phantom assembly in the BOM.
- D. Change the phantom item indicator for the phantom assembly in the BOM.
Answer: C
NEW QUESTION 46
......
Dumps for Free C_TS422_2021 Practice Exam Questions: https://examtorrent.vce4dumps.com/C_TS422_2021-latest-dumps.html